London Colney still waiting for Shenley Lane improvements after eight years

PUBLISHED: 10:10 13 September 2017 | UPDATED: 10:17 13 September 2017

The 30 mph speed limit sign on Shenley Lane. Picture: Danny Loo

The 30 mph speed limit sign on Shenley Lane. Picture: Danny Loo

Danny Loo Photography 2017

London Colney villagers say they are still waiting for traffic calming measures on Shenley Lane eight years after the scheme was agreed.

Residents are calling for traffic-calming measures on Shenley Lane. Picture: Danny Loo Residents are calling for traffic-calming measures on Shenley Lane. Picture: Danny Loo

A 2009 petition by residents and district councillor Dreda Gordon pressured Herts county council (HCC) into agreeing to install traffic calming measures.

But the works have been delayed while a utility company carries out work on the road.

Cllr Gordon said: “It does not seem to be a very satisfactory way of working, and has disappointed local people and me.

“Shenley Lane is a busy thoroughfare, with a 30mph speed limit, but speeding has always been an issue, so the petition from residents was to introduce traffic calming measures.

“It’s a residential road, as there is the new Napsbury 
estate, but it’s also very dark 
and dangerous one.

“There are police checks, which is why the council accepted it was a priority.”

In December 2012, 13-year-old Daniel Handscombe was killed when he was hit by two cars crossing Shenley Lane.

Following Daniel’s death, Cllr Gordon demanded speed cameras be installed along the road, and HCC promised to look into it.

In 2015, they agreed to new traffic calming measures, but the work was delayed.

The works were then supposed to start in May this year, but were again put off until August bank holiday.

But Cllr Gordon said there have been further delays while a utility company digs up the road, and it now looks like the work will not start until next year.

“I just can’t believe there is this lack of joined-up thinking between utilities and the county council.

“They could have coordinated the whole thing together, rather than it happening in this lopsided manner.”

A HCC spokesperson said: 
“We understand residents’ concerns and want to reassure them that our contractor Ringway will carry out the 
works on behalf of the county council.

“These works have, however, been delayed to allow for 
Cadent to carry out essential main replacement works on Shenley Lane. Unfortunately, this scheme has resulted in the postponement of the carriageway resurfacing works until later this financial year. We aim to complete all of the works by the end of March 2018 and thank residents for their patience.”

More news stories

18 minutes ago

Sheep shearing demonstrations will form part of the May half-term holiday fun at a popular activity farm.

53 minutes ago

Cleaning signs and clearing overgrown vegetation might usually be down to the council – but in pockets of Herts volunteers have been rolling up their sleeves themselves.

St Albans district’s police force has been bolstered by a new neighbourhood sergeant and police community support officer.

11:00

Rennie Grove Hospice Care has joined with other hospice care providers in the UK to raise the profile of children’s palliative care during Children’s Hospice Week. This year the theme is “Life’s short”.

CountryPhile

Digital Edition

Image
Read the The Herts Advertiser e-edition E-edition

Local business directory

Hertfordshire's trusted business finder
Zoo Watch CountryPhile

Newsletter Sign Up

Sign up to receive our regular email newsletter

Most read stories

HOT JOBS

Show Job Lists

Herts Most Wanted Herts Business Awards